No
|
Title
|
Duration
|
Implemented by
|
Progress %
(March 2016)
|
Status
|
Start
|
End
|
Plan
|
Actual
|
1
|
Construction of Persian Gulf Star Gas condensate Refinery
|
2007
|
2016
|
Persian
Gulf Star Oil Refinery Company
|
94.68
|
87.07
|
-
|
Refinery construction
|
2008
|
2016
|
93.74
|
84.8
|
-
|
36" Feed stock Pipeline
|
2008
|
2015
|
100
|
99.99
|
-
|
Sea Water Intake project (onshore)
|
2008
|
2015
|
100
|
99.89
|
-
|
Development & Optimization of existing Refineries
|
2
|
Process Improvement & Optimization of Lavan Refinery
|
2005
|
2015
|
Lavan Oil Refinery Company
|
-
|
-
|
Completion
May 2016
|
Licence Units
|
2007
|
2013
|
-
|
-
|
All units already implemented & ready to hand over
|
Off-site facilities Units
|
2007
|
2013
|
|
|
Accomplished
|
3
|
Process optimization & quality improvement of Tehran Refinery products
|
2007
|
2015
|
NIOEC
|
100
|
99.98
|
eady to hand over & pay off,
GTG project ongoing
|
4
|
Capacity Increasement & quality improvement of Arak (Shazand) Refinery products
|
2002
|
2015
|
NIOEC
|
100
|
99.84
|
Final hand over & pay off
|
No
|
Title
|
Duration
|
Implemented by
|
Progress %
(March 2016)
|
Status
|
Start
|
End
|
Plan
|
Actual
|
5
|
Process Development & Optimization of Esfahan Refinery
|
2003
|
2025
|
NOIEC
|
-
|
-
|
-
|
Development & Optimization of
Esfahan Refinery (DRP)
|
2007
|
-
|
99.67
|
29.38
|
-
|
Process Development & Optimization of Esfahan Refinery
|
2003
|
-
|
100
|
16.03
|
-
|
6
|
Development & Capacity Stabilization of Abadan Refinery
|
2006
|
2020
|
NIOEC
|
7.52
|
4.16
|
Engineering stage of EWA is completed
|
Optimization & Construction of Gasoline Production Units
|
7
|
FCC & related Units Construction of Abadan Refinery
|
2006
|
2015
|
Abadan Oil Refinery Company
|
-
|
-
|
Alkylation unit yet to be in service
|
8
|
Maximising Gasoline Production of Bandar Abbas Refinery
|
2006
|
2016
|
NIOEC
|
98.35
|
95.15
|
-
|
Crude Oil & Petroleum Product Transportation
|
9
|
Abadan-Mahshahr Pipeline
|
2006
|
2015
|
NIOEC
|
-
|
-
|
Resolving deficiencies /26" fuel oil pipeline in Back area already launched
|
Construction of additional 26" fuel oil pipeline Back area-Mahshahr
|
2012
|
2015
|
100
|
96.98
|
provisional delivery to operator
|
No
|
Title
|
Duration
|
Implemented by
|
Progress %
(March 2016)
|
Status
|
Start
|
End
|
Plan
|
Actual
|
10
|
Construction of Storage facilities and Pump Stations in Abadan-Mahshahr
|
2008
|
2017
|
NIOEC
|
7.7
|
4.3
|
-
|
11
|
Bandar Mahshar Reorganizing project
|
2005
|
2016
|
NIOEC
|
96.95
|
93.87
|
provisional delivery to operator
|
Designing, Reconstruction & Renovation of Bandar Mahshahr (Phase-1)
|
2005
|
2012
|
-
|
-
|
Designing & Construction of Sulphur export & storage facilities
|
2010
|
2013
|
-
|
-
|
Construction of two 24" product pipelines from New storage Tank of
(Noor-bakhsh) to Bandar Mahshahr
|
2013
|
2016
|
99.5
|
99.2
|
12
|
Construction of Abadan-Arak-Rey pipeline
|
2007
|
2015
|
NIOEC
|
100
|
28.01
|
-
|
13
|
Construction of Sabz ab/ Tange Fanni-Shazand-Rey sour crude pipeline
|
2015
|
2019
|
NIOEC
|
4.97
|
4.97
|
Obtaining environmental permits, land acquisition for pump stations & financial
considerations
|
No
|
Title
|
Duration
|
Implemented by
|
Progress %
(March 2016)
|
Status
|
Start
|
End
|
Plan
|
Actual
|
14
|
Construction of 20" Naiin-Kashan-Rey product transportation pipeline Project & related facilities
|
2012
|
2017
|
NIOEC
|
94.07
|
55.32
|
Slow progress due to financial consideration
|
15
|
Development of petroleum product transportation pipeline
|
2012
|
2017
|
NIOEC
|
-
|
-
|
-
|
Capacity increasement of
Tabriz- Khoy-Orumieh pipeline
|
2012
|
2017
|
78.57
|
66.87
|
land acquisition for pipeline &
pumping station yet to be finalized
|
16
|
Construction of Bandar Abbas-Sirjan-Rafsanjan 26" product pipeline
|
2014
|
2018
|
NIOEC
|
31.55
|
6.33
|
Detail designing & basic engineering revision
|
Iranian Oil Pipeline & Telecommunication Company (NIOPTC) Projects
|
17
|
Construction of Tehran bypass pipeline
(passive Defence project)
|
2013
|
2015
|
NIOPTC
|
-
|
-
|
-
|
|
|
|
|
|
|
|
|
|